Topaze Guided Session #4
TopGS04 - 14/16
Click now on the Run Simulation (
) button, and change the final initial rate to 4100
STB/D before to proceed with the Topaze field simulation:
Fig. B15 • Topaze main screen after field simulation
A total of 116 producers and 12 injectors were scheduled by the simulation.
B02.2 • Adding Constraints
Let us now assume that for logistic reasons the total oil rate cannot exceed 350,000 STB/D. To
enter this constraint, click on the General Input button in the Constraints tab, and enter
350,000 STB/D in the Oil rate column for a constraint starting in January 2012:
Keep this constraint as ‘Flag only’ for the time being, and click on OK to visualize it in the field
production graph (click on the option):