This dialog defines the basic settings required for the creation of the Saphir interpretation file
(which well should be taken as reference well, which productions are to be transferred, etc...).
In our case:
Prod 1 will be the reference well of the
Saphir file (it is the only well in the sector
anyway):
We do not need to copy the complete well
history as we want to investigate the last
build-up. Change the copy start date from
January 1
st
1999 to October 1
st
2005.
Click on Synchronize to adjust the start
date to an existing restart:
Accept all other default settings and click on ‘Create Saphir Document >>’ to switch to Saphir:
Fig. B01.8 • Saphir document built from the Rubis sector