Ecrin v4.12 - Doc v4.12.02 - © KAPPA 1988-2009
Rubis Guided Session #3
• Rub
GS03 - 17/22
C01 • Running Alternative Scenarios
C01.1 • Opening the Producer Top Perforation
We will evaluate now how the oil production is affected if the (always closed so far) producer
top perforation is opened during the life of the reservoir. First, click on in the run toolbar to
create a new run by copy of the Base one – name this run “Perf”:
Fig. C01.1 • Creating the “Perf” run
In this new run, edit the wells by clicking on the “Wells” button in the Simulation page. Select
the producer and click on “Perforations”, then change the top perforation opening time from
January 15
th
, 2020 to January 18
th
, 2014:
Fig. C01.2 • Top perforation opening time, before (top) and after (bottom) the changes
Edit the producer controls, and click twice on the Add button to add two more lines in the grid:
Change the starting dates of the two new controls to
January 15
th
, 2014 and January 18
th
, 2014, respectively: